PumpedHydro
Not prioritised by Queensland Government / EIS remains active APH-PLAN-005

Mt Rawdon Pumped Hydro

Approximately 75 km southwest of Bundaberg · Queensland

Mt Rawdon Pumped Hydro is a proposed energy storage scheme that would reuse the Mount Rawdon gold mine pit as a lower reservoir near Bundaberg, Queensland.

2,000 MW · generation
20 GWh · storage
10 hours · design duration

Overview

Mt Rawdon Pumped Hydro is a proposed energy storage scheme that would reuse the Mount Rawdon gold mine pit as a lower reservoir near Bundaberg, Queensland. The planning register describes up to 20 GWh of storage, a new upper reservoir and connection to the Powerlink network. The register still lists an active EIS and an indicative A$6.14 billion investment. Evolution Mining disclosed that QIC advised in June 2026 that the Queensland Government would not prioritise the project. An active assessment listing therefore does not establish government funding or a committed construction pathway.

Evolution FY26 results confirm June 2026 QIC advice that state government will not prioritise Mt Rawdon. Planning register remains EIS active.

Key technical details

Developer / ownerMt Rawdon Pumped Hydro Pty Ltd; Evolution Mining project interest confirmed, current equity split unconfirmed
Scheme typeMine-site PHES
Open / closed loopClosed-loop / off-river mine-site
Greenfield / brownfieldBrownfield
Reservoir configurationMine pit lower reservoir and purpose-built upper reservoir.
Lower reservoirMt Rawdon mine pit
Upper reservoirPurpose-built upper reservoir
Water source / first fillFirst fill likely from Paradise Dam via pipeline upgrades.
Grid / REZ connectionConnection to Powerlink network
Power / energy basisUp to 20,000 MWh confirmed by current state register. Previously recorded 2,000 MW / 10h configuration not independently reconfirmed.
Brownfield basisRepurposes existing Mt Rawdon open-cut gold mine pit as lower reservoir.

Status, approvals & verification

StatusNot prioritised by Queensland Government / EIS remains active
Status detailEvolution FY26 results confirm June 2026 QIC advice that state government will not prioritise Mt Rawdon. Planning register remains EIS active.
Planning / approvals statusEIS active on Coordinator-General page; public support status changed in 2026.
Pipeline classificationProposal; exclude from committed totals
Verification resultReviewed; some legacy fields unconfirmed
Unconfirmed legacy fieldsCapacity MW; Duration hours
Capacity basis2,000 MW legacy configuration not reconfirmed; 20 GWh source supported
Storage basisPublished design / tender figure; see qualifications
Cost basisIndicative published estimate; not a funding commitment or current outturn
Last checked2026-11-10
Source access limitationsPublic page text or indexed primary-source evidence reviewed; publisher updates may lag events.

Economics

Estimated costA$6.14 bn
Jobs (construction)780
Jobs (operating)30

Sources & location

Primary source ↗ Secondary source ↗ Reviewed evidence 1 ↗ Reviewed evidence 2 ↗

Source quality: Owner / regulator evidence; see field-level qualifications

Indicative location
Mount Perry region · Queensland
Regional anchor — not a verified project-site coordinate.
Anchor source ↗
View on the full map →
← Back to all projects

Working on this project?

Share useful sources, ask practical questions and connect with others interested in Australian pumped hydro.

Professional enquiries Join the LinkedIn group