Feasibility proposal / current progress unconfirmed APH-PLAN-014

Central West Pumped Hydro

Near Yetholme / Central West NSW · New South Wales

Central West Pumped Hydro is an ATCO Australia feasibility proposal in the Central West of New South Wales.

325 MW · generation
2.6 GWh · indicative
8 hours · design duration

Overview

Central West Pumped Hydro is an ATCO Australia feasibility proposal in the Central West of New South Wales. EnergyCo’s recoverable-grants register lists 325 MW and eight hours of storage, implying 2.6 GWh at rated output. Engineering consultant WSP has described work supporting the project near Yetholme. These sources establish the proposal and its study design, but do not confirm that construction has begun or that an investment decision has been made. A current ATCO delivery schedule, detailed reservoir arrangement and commissioning date were not established in this review.

EnergyCo grants register retains feasibility classification; current owner milestone not confirmed.

Key technical details

Developer / ownerATCO Australia
Scheme typePHES feasibility project
Open / closed loopTo confirm
Greenfield / brownfieldGreenfield
Reservoir configurationPlanned reservoirs to confirm.
Lower reservoirTBC
Upper reservoirTBC
Water source / first fillTBC
Grid / REZ connectionCentral West NSW; detailed connection not confirmed
Power / energy basisEnergyCo grant-register design: 325 MW / 8h; 2.6 GWh calculated. Not a current committed-capacity statement.
Brownfield basisNo existing reservoir or mine-pit reuse confirmed from public summary.

Status, approvals & verification

StatusFeasibility proposal / current progress unconfirmed
Status detailEnergyCo grants register retains feasibility classification; current owner milestone not confirmed.
Planning / approvals statusFeasibility supported by recoverable grant; current detailed approvals status unconfirmed.
Target COD / timingTBC
Pipeline classificationCurrent progress unconfirmed; exclude from committed totals
Verification resultHistorical study design confirmed; current progress unconfirmed
Capacity basisPublished proposal or study design; not committed capacity
Storage basisCalculated / indicative; see power/energy basis
Cost basisNot confirmed / not applicable
Last checked2026-11-10
Source access limitationsPublic page text or indexed primary-source evidence reviewed; publisher updates may lag events.

Sources & location

Primary source ↗ Secondary source ↗ Reviewed evidence 1 ↗ Reviewed evidence 2 ↗

Source quality: Historical primary evidence; current progress unconfirmed

Indicative location
Bathurst / Central West region · New South Wales
Regional anchor — not a verified project-site coordinate.
Anchor source ↗
View on the full map →
← Back to all projects

Working on this project?

Share useful sources, ask practical questions and connect with others interested in Australian pumped hydro.

Professional enquiries Join the LinkedIn group