Borumba Pumped Hydro Energy Storage

Lake Borumba / Imbil · Queensland

Borumba Pumped Hydro Energy Storage is a proposed 2,000 MW project near Imbil in Queensland.

2,000 MW · generation
48 GWh · storage
24 hours · design duration

Overview

Borumba Pumped Hydro Energy Storage is a proposed 2,000 MW project near Imbil in Queensland. The planning design provides up to 48 GWh of storage, equivalent to 24 hours at rated output, using an expanded Lake Borumba and a new upper reservoir. Queensland Hydro is the proponent. The state register lists an active environmental impact statement process, while QIC is undertaking further commercial assessment of Borumba and Capricornia. Queensland Hydro’s 2025 financial statements reported an A$18.4 billion estimate, superseding the A$14.2 billion figure still displayed on the planning register. A final delivery commitment remains unresolved.

EIS active; draft being prepared. QIC further assessment continues; exploratory works are separate from main-project approval.

Key technical details

Developer / ownerQueensland Hydro / QIC oversight
Scheme typeLong-duration PHES
Open / closed loopOpen-loop / existing dam expanded
Greenfield / brownfieldHybrid brownfield / greenfield
Reservoir configurationExpanded Lake Borumba as lower reservoir; new upper reservoir.
Lower reservoirLake Borumba
Upper reservoirNew upper reservoir formed by main and saddle dams
Water source / first fillLake Borumba / Mary River catchment; water security role under review.
Grid / REZ connectionTransmission network connection under development; specific route not reconfirmed.
Power / energy basisPlanning design: up to 2,000 MW for 24 hours, 48,000 MWh.
Brownfield basisExpands existing Lake Borumba lower reservoir; builds new upper reservoir and new dam infrastructure.

Status, approvals & verification

StatusPlanning / EIS and commercial assessment
Status detailEIS active; draft being prepared. QIC further assessment continues; exploratory works are separate from main-project approval.
Planning / approvals statusEIS active; EPBC under assessment.
Target COD / timingUnconfirmed; QIC identifies system need from mid-2030s
Pipeline classificationProposal; exclude from committed totals
Verification resultReviewed; some legacy fields unconfirmed
Unconfirmed legacy fieldsWater source / first fill
Capacity basisPublished proposal or study design; not committed capacity
Storage basisPublished design / tender figure; see qualifications
Cost basis2025 owner financial statements; register retains older A$14.2bn
Last checked2026-11-10
Source access limitationsPublic page text or indexed primary-source evidence reviewed; publisher updates may lag events.

Economics

Estimated costA$18.4 bn
Jobs (construction)2360
Jobs (operating)30

Sources & location

Primary source ↗ Secondary source ↗ Reviewed evidence 1 ↗ Reviewed evidence 2 ↗ Reviewed evidence 3 ↗

Source quality: Owner / regulator evidence; see field-level qualifications

Indicative location
Imbil region · Queensland
Regional anchor — not a verified project-site coordinate.
Anchor source ↗
View on the full map →
← Back to all projects

Working on this project?

Share useful sources, ask practical questions and connect with others interested in Australian pumped hydro.

Professional enquiries Join the LinkedIn group