PumpedHydro
Early development APH-PLAN-010

Glenbawn Pumped Hydro Energy Storage

Glenbawn Dam / Upper Hunter · New South Wales

Glenbawn Pumped Hydro Energy Storage is AGL's proposed approximately 800 MW project at Glenbawn Dam, about 15 kilometres east of Scone in the Upper Hunter, New South Wales.

800 MW · generation
8 GWh · storage
10 hours · design duration

Overview

Glenbawn Pumped Hydro Energy Storage is AGL’s proposed approximately 800 MW project at Glenbawn Dam, about 15 kilometres east of Scone in the Upper Hunter, New South Wales. AGL publishes a ten-hour design and up to 8 GWh of storage. The existing dam would form the lower reservoir, with a new upper reservoir and generation infrastructure on WaterNSW land. AGL acquired the project through Upper Hunter Hydro in May 2025. Geotechnical investigations have commenced and a scoping report is being prepared. Environmental assessment, approvals and an investment decision remain ahead.

Initial investigation phase; geotechnical investigations commenced and scoping report being prepared.

Key technical details

Developer / ownerAGL
Scheme typeWaterNSW land/assets PHES
Open / closed loopOpen-loop / existing dam linked
Greenfield / brownfieldHybrid brownfield / greenfield
Reservoir configurationExisting Glenbawn Dam and new upper reservoir.
Lower reservoirGlenbawn Dam
Upper reservoirNew upper reservoir
Water source / first fillWaterNSW dam for initial fill and top-ups; water recirculated between reservoirs.
Grid / REZ connectionProposed Hunter–Central Coast REZ; detailed connection design under development
Power / energy basisCurrent AGL project page: approximately 800 MW / 10 hours / 8 GWh. Acquisition announcement used 770 MW.
Brownfield basisUses existing Glenbawn Dam as lower reservoir; builds new upper reservoir.

Status, approvals & verification

StatusEarly development
Status detailInitial investigation phase; geotechnical investigations commenced and scoping report being prepared.
Planning / approvals statusEarly investigations and scoping; NSW state-significant assessment pathway.
Target COD / timingTBC
Pipeline classificationProposal; exclude from committed totals
Verification resultReviewed; source-supported with stated qualifications
Capacity basisPublished proposal or study design; not committed capacity
Storage basisPublished design / tender figure; see qualifications
Cost basisNot confirmed / not applicable
Last checked2026-11-10
Source access limitationsPublic page text or indexed primary-source evidence reviewed; publisher updates may lag events.

Sources & location

Primary source ↗ Secondary source ↗ Reviewed evidence 1 ↗ Reviewed evidence 2 ↗ Reviewed evidence 3 ↗

Source quality: Owner / regulator evidence; see field-level qualifications

Indicative location
Scone / Upper Hunter region · New South Wales
Regional anchor — not a verified project-site coordinate.
Anchor source ↗
View on the full map →
← Back to all projects

Working on this project?

Share useful sources, ask practical questions and connect with others interested in Australian pumped hydro.

Professional enquiries Join the LinkedIn group